XML Structure of the <Task> Element
The following shows the <Task> element structure for Microsoft Office Project 2003, which is a child of the <Project> element.
See Also
Overview of XML Schema for Project
Overview of XML Structure for Project
XML Structure for the <Project> Element
XML Schema for the <Task> Element
Structure
<Project>
. . .
<Tasks>
<Task>
<UID/>
<ID/>
<Name/>
<Type/>
<IsNull/>
<CreateDate/>
<Contact/>
<WBS/>
<WBSLevel/>
<OutlineNumber/>
<OutlineLevel/>
<Priority/>
<Start/>
<Finish/>
<Duration/>
<DurationFormat/>
<Work/>
<Stop/>
<Resume/>
<ResumeValid/>
<EffortDriven/>
<Recurring/>
<OverAllocated/>
<Estimated/>
<Milestone/>
<Summary/>
<Critical/>
<IsSubproject/>
<IsSubprojectReadOnly/>
<SubprojectName/>
<ExternalTask/>
<ExternalTaskProject/>
<EarlyStart/>
<EarlyFinish/>
<LateStart/>
<LateFinish/>
<StartVariance/>
<FinishVariance/>
<WorkVariance/>
<FreeSlack/>
<TotalSlack/>
<FixedCost/>
<FixedCostAccrual/>
<PercentComplete/>
<PercentWorkComplete/>
<Cost/>
<OvertimeCost/>
<OvertimeWork/>
<ActualStart/>
<ActualFinish/>
<ActualDuration/>
<ActualCost/>
<ActualOvertimeCost/>
<ActualWork/>
<ActualOvertimeWork/>
<RegularWork/>
<RemainingDuration/>
<RemainingCost/>
<RemainingWork/>
<RemainingOvertimeCost/>
<RemainingOvertimeWork/>
<ACWP/>
<CV/>
<ConstraintType/>
<CalendarUID/>
<ConstraintDate/>
<Deadline/>
<LevelAssignments/>
<LevelingCanSplit/>
<LevelingDelay/>
<LevelingDelayFormat/>
<PreLeveledStart/>
<PreLeveledFinish/>
<Hyperlink/>
<HyperlinkAddress/>
<HyperlinkSubAddress/>
<IgnoreResourceCalendar/>
<Notes/>
<HideBar/>
<Rollup/>
<BCWS/>
<BCWP/>
<PhysicalPercentComplete/>
<EarnedValueMethod/>
<PredecessorLink>
<PredecessorUID/>
<Type/>
<CrossProject/>
<CrossProjectName/>
<LinkLag/>
<LagFormat/>
</PredecessorLink>
<ActualWorkProtected/>
<ActualOvertimeWorkProtected/>
<ExtendedAttribute>
<UID/>
<FieldID/>
<Value/>
<ValueID/>
<DurationFormat/>
</ExtendedAttribute>
<Baseline>
<TimephasedData>
<Type/>
<UID/>
<Start/>
<Finish/>
<Unit/>
<Value/>
</TimephasedData>
<Number/>
<Interim/>
<Start/>
<Finish/>
<Duration/>
<DurationFormat/>
<EstimatedDuration/>
<Work/>
<Cost/>
<BCWS/>
<BCWP/>
</Baseline>
<OutlineCode>
<UID/>
<FieldID/>
<ValueID/>
</OutlineCode>
<TimephasedData>
<Type/>
<UID/>
<Start/>
<Finish/>
<Unit/>
<Value/>
</TimephasedData>
</Task>
</Tasks>
. . .
</Project>