<RemainingCost> Element
For a <Task>, <RemainingCost> is the remaining scheduled expense of a task that will be incurred in completing the remaining scheduled work by all resources assigned to a task.
For a <Resource>, it is the remaining scheduled expense that will be incurred in completing the remaining work assigned to a resource.
For an <Assignment>, it is the costs associated with completing all remaining scheduled work by any resources on a specific task.
Element Properties
Property | Value |
---|---|
Data Type | Decimal |
Minimum Occurrences | 0 |
Maximum Occurrences | 1 |
Default Value | N/A |
Abstract | False |
Nillable | False |
Element Constraints | N/A |