<Baseline> Element

The collection of baseline values associated with the task, resource or assignment.

Element Properties

Property Value
Data Type ComplexType
Minimum Occurrences 0
Maximum Occurrences Unbounded
Default Value N/A
Abstract False
Nillable False
Element Constraints Sequence

Parent Elements

Task
Resource
Assignment

Child Elements for &lt;Task&gt;

List of <Baseline> Child Elements for <Task>

Element Required/Optional Description
<TimephasedData> Optional The timephased data block associated with the task baseline.
<Number> Required The unique number of the baseline data record.
<Interim> Optional Indicates whether the baseline is an interim baseline.
<Start> Optional The scheduled start date of the task when the baseline was saved.
<Finish> Optional The scheduled finish date of the task when the baseline was saved.
<Duration> Optional The scheduled duration of the task when the baseline was saved.
<DurationFormat> Optional The format for expressing the duration of the task baseline.
<EstimatedDuration> Optional Indicates whether the duration of the task is estimated.
<Work> Optional The scheduled work for the task when the baseline was saved.
<Cost> Optional The projected cost of the task when the baseline was saved.
<BCWS> Optional The cumulative timephased baseline costs up to the status date or today's date; also known as budgeted cost of work scheduled.
<BCWP> Optional The cumulative value of the task's timephased percent complete multiplied by the task's timephased baseline cost, up to the status date or today's date; also known as budgeted cost of work performed.

Child Elements for &lt;Resource&gt;

List of <Baseline> Child Elements for <Resource>

Element Required/Optional Description
<Number> Required The unique number of the baseline data record.
<Work> Optional The work assigned to the resource when the baseline is saved.
<Cost> Optional The projected cost for the resource when the baseline was saved.
<BCWS> Optional The budgeted cost of work scheduled for the resource.
<BCWP> Optional The budgeted cost of the work performed by the resource on the project to-date.

Child Elements for &lt;Assignment&gt;

List of <Baseline> Child Elements for <Assignment>

Element Required/Optional Description
<TimephasedData> Optional The timephased data block associated with the task baseline.
<Number> Required The unique number of the baseline data record.
<Start> Optional The scheduled start date of the assignment when the baseline was saved.
<Finish> Optional The scheduled finish date of the assignment when the baseline was saved.
<Work> Optional The total amount of work scheduled on the assignment when the baseline was saved.
<Cost> Optional The total projected cost of the assignment when the baseline was saved.
<BCWS> Optional The budgeted cost of work scheduled on the assignment.
<BCWP> Optional The budgeted cost of the work performed on the assignment to-date.

See Also

XML Schema for the <Task> Element
XML Structure for the <Task> Element

XML Schema for the <Resource> Element
XML Structure for the <Resource> Element

XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element