<BCWP> Element

BCWP is the Budgeted Cost of Work Performed.

For a <Task>, it is the cumulative value of the task's timephased percent complete multiplied by the task's timephased baseline cost, up to the status date or today's date.

For a <Resource>, it is the rolled-up summary of a resource's BCWP values for all assigned tasks, calculated up to the status date or today's date.

For an <Assignment>, it is the budgeted cost of the work performed on the assignment to date.

For a <Baseline> in a <Task>, it is the cumulative value of the task's timephased percent complete multiplied by the task's timephased baseline cost, up to the status date or today's date.

For a <Baseline> in a <Resource>, it is the budgeted cost of the work performed by the resource on the project to-date.

For a <Baseline> in an <Assignment>, it is the budgeted cost of the work performed on the assignment to-date.

Element Properties

Property Value
Data Type Decimal
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints N/A

Parent Elements

Task
Resource
Assignment
Baseline

See Also

XML Schema for the <Task> Element
XML Structure for the <Task> Element

XML Schema for the <Resource> Element
XML Structure for the <Resource> Element

XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element

<Baseline> Element
<BCWS> Element
<PhysicalPercentComplete> Element