<ActualCost> Element

For a <Task>, <ActualCost> is the costs incurred for work already performed by all resources on a task, along with any other recorded costs associated with the task.

For a <Resource>, it is the sum of costs incurred for the work already performed by a resource for all assigned tasks.

For an <Assignment>, it is the cost incurred for work already performed by a resource on a task.

Element Properties

Property Value
Data Type Decimal
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints N/A

Parent Elements

Task
Resource
Assignment

See Also

XML Schema for the <Task> Element
XML Structure for the <Task> Element

XML Schema for the <Resource> Element
XML Structure for the <Resource> Element

XML Schema for the <Assignment> Element
XML Structure for the <Assignment> Element