<ActualDuration> Element

The span of actual working time for a task so far, based on the scheduled duration and current remaining work or percent complete. Actual duration can be calculated in two ways, either based on percent complete or remaining duration.

Element Properties

Property Value
Data Type Duration
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints N/A

Parent Elements

Task

See Also

XML Schema for the <Task> Element
XML Structure for the <Task> Element