Ending Date Field, Assembly Header Table

Specifies the date on which the assembly order is expected to finish. This is the date on which all assembly items are output.

The value is calculated as follows:

ending date = starting date + lead time calculation

Additional Information

The Ending Date field is related to the Due Date field on the assembly order header as follows:

ending date + safety lead time + warehouse handling time = due date

If the assembly order is linked to a sales order, then the field is automatically filled according to the Shipment Date field on the sales order line, through the assembly order Due Date field.

Warning

The date in the Ending Date field must not be later than the date in the Posting Date field.

This field and the Due Date field are updated when you change the Starting Date field.

Note

The Due Date field is not updated if the assembly order is linked to a sales order.

Tip

For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.

Parent Tables

Table Location
Unit of Measure Code Field, Assembly Header Table Warehouse Management
Assembly Header Table Warehouse Management
Assembly Header Table Warehouse Management

See Also

Reference

Assembly Order
Lead-Time Offset
Due Date
Starting Date
Posting Date
Posting Date

Other Resources

Lead Time Calculation
Shipment Date
How to: Assemble Items to Order