Lead Time Calculation Field, Item Table

Specifies a date formula for the amount of time that it takes to replenish the item. This field is used to calculate the date fields on order and order proposal lines.

Additional Information

Date fields on order and order proposal lines are calculated as follows:

On a purchase order line, the Order Date + Lead Time Calculation = Planned Receipt Date.

On an assembly order, the Starting Date + Lead Time Calculation = Ending Date.

On a production order line, the Starting Date + Lead Time Calculation = Ending Date.

Note

If the produced item uses a routing, then this is used to calculate the ending date. The lead time calculation is only used if the item does not have a routing.

When the Lead Time Calculation field is filled in several windows, it is prioritized as follows:

  1. Item vendor card

  2. Stockkeeping unit card

  3. Item card

Example

If a purchase is ordered on December 20. (Order Date: 12/20), and the lead time is two days (Lead Time Calculation: 2D), then the purchased items can be expected at the delivery address on December 22. (Planned Receipt Date: 12/22).

Tip

For more information on how to work with fields and columns, see Work with Data. For assistance in finding specific pages, see Search.

Parent Tables

Table Location
Negative Adjmt. (LCY) Field, Item Table Inventory
Item Table Inventory
Item Table Inventory

See Also

Reference

Item Vendor
Stockkeeping Unit
Item Card

Other Resources

Order Date
Ending Date
Planned Receipt Date
Starting Date
Ending Date
Routing Line