StartVariance Element
For a Task, StartVariance is the difference between a task's baseline start date and its currently scheduled start date.
For an Assignment, it is the difference between an assignment's baseline start date and its currently scheduled start date.
<StartVariance>
IntegerValue
</StartVariance>