LevelingDelay Element
For a Task, LevelingDelay is the amount of time that a task is to be delayed from its early start date as a result of resource leveling.
For an Assignment, it is the total amount of work scheduled to be performed by a resource on a task.
<LevelingDelay>
IntegerValue
</LevelingDelay>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
Remarks
A LevelingDelay requires the LevelingDelayFormat to be specified. For example, a leveling delay of 3 days in a task is expressed as follows:
<Task>
...
<LevelingDelay>3</LevelingDelay>
<LevelingDelayFormat>7</LevelingDelayFormat>
...
</Task>
See Also
Reference
Concepts
Task Elements and XML Structure
XML Schema for the Tasks Element