Freigeben über


Manage your Scrum process work item types and workflow

Azure DevOps Services | Azure DevOps Server 2022 - Azure DevOps Server 2019 | TFS 2018 - TFS 2013

To plan a software project and track software defects using Scrum, teams use the product backlog item (PBI) and bug work item types (WITs). To gain insight into a portfolio of features, scenarios, or user experiences, product owners, and program managers can map PBIs and bugs to features. When teams work in sprints, they define tasks that automatically link to PBIs and bugs.

Scrum process, WITs used to plan and track

Note

If you are new to the Scrum process, review About Sprints, Scrum and project management to get started.

Using the web portal or Microsoft Test Manager, testers can create and run test cases and create bugs to track code defects. Impediments track blocking issues.

Note

Work item tracking forms and features available to you differ depending on whether you open the form from the web portal or Visual Studio Team Explorer. Forms and guidance provided in this article reflect those available with the new form experience (Azure DevOps Services and TFS 2017 and later versions).

For guidance on the work item form for TFS 2015 or earlier versions or Visual Studio Team Explorer, see Add work items and select the earlier TFS version from the content version selector (above the table of contents).

Define PBIs and bugs

When you define a product backlog item, you want to focus on the value that your customers will receive and avoid descriptions of how your team will develop the feature. The product owner can prioritize your product backlog based on each item's business value, effort, and relative dependency on other backlog items. As your business requirements evolve, so does your product backlog. Typically, teams specify details only for the highest priority items, or those items assigned to the current and next sprint.

You can create PBIs and bugs from the quick add panel on the product backlog page.

Web portal, Agile process, Quick add panel

Later, you can open each PBI or bug to provide more details and estimate the effort. Also, by prioritizing the PBIs and bugs on the backlog page (which is captured in the Backlog Priority field), product owners can indicate which items should be given higher priority.

Product backlog item work item form

By defining the Effort for PBIs and bugs, teams can use the forecast feature and velocity charts to estimate future sprints or work efforts. By defining the Business Value, product owners can specify priorities separate from the changeable backlog stack ranking.

Use the following guidance and that provided for fields used in common across work item types when filling out the form. For details about creating bugs, see Manage bugs.

Field/tab

Usage

Estimate the amount of work required to complete a PBI using any unit of measurement your team prefers, such as story points or time. A numeric value is required.

Agile velocity charts and forecast tools reference the values in this field. For more information, see the Estimating white paper.

Specify a number that captures the relative value of a PBI compared to other PBIs. The higher the number, the greater the business value.

Provide enough detail for estimating how much work will be required to implement the item. Focus on who the feature is for, what users want to accomplish, and why. Don't describe how the feature should be developed. Do provide sufficient details so that your team can write tasks and test cases to implement the item.

Define what "Done" means by describing the criteria that the team should use to verify whether the PBI or the bug fix has been fully implemented.

Before work begins on a PBI or bug, describe the criteria for customer acceptance as clearly as possible. Conversations between the team and customers to determine the acceptance criteria helps ensure a common understanding within the team to meet customers' expectations. The acceptance criteria can be used as the basis for acceptance tests so that the team can more effectively evaluate whether an item has been satisfactorily completed.

Capture comments in the Discussion section

Use the Discussion section to add and review comments made about the work being performed.

Discussion section within a work item form

Use the @mention control to notify another team member about the discussion. Simply type @ and their name. To reference a work item, use the #ID control. Type # and a list of work items that you've recently referenced will appear from which you can select.

To reference a work item, use the #ID control. Type # and a list of work items that you've recently referenced will appear from which you can select.

You can't edit or delete comments once you've entered them.

Important

For on-premises Azure DevOps Server, you must configure an SMTP server in order for team members to receive notifications.

Track progress

As work progresses, you change the State field to update the status. Optionally, you can specify a reason. The state and reason fields appear on the work item form in the header area.

Bug work item form, header area

Scrum workflow states

By updating the State, teams know which items are new, in progress, or completed. Most WITs support transition both forward and backward from each workflow state. These diagrams show the main progression and regression states of the PBI, bug, and task WITs.

Product Backlog Item Bug Task
Product Backlog Item workflow states, Scrum process Bug workflow states, Scrum process Task workflow states, Scrum process

PBIs and bugs follow this typical workflow progression:

  • The product owner creates a PBI or a tester creates a bug in the New state with the default reason, New backlog item
  • The product owner moves the item to Approved after it's sufficiently described and ready for the team to estimate the level of effort. Most of the time, items near the top of the Product Backlog are in the Approved state, while items toward the middle and bottom are in a New state
  • The team updates the status to Committed when they decide to commit to working on it during the sprint
  • The item is moved to the Done state when the team has completed all its associated tasks and the product owner agrees that it has been implemented according to the Acceptance Criteria.

Update status with Kanban or taskboards

Teams can use the Kanban board to update the status of PBIs, and the sprint taskboard to update the status of tasks. Dragging items to a new state column updates both the State and Reason fields.

Track progress on the Kanban board

You can customize the Kanban board to support more swim lanes or columns. For other customization options, see Customize your work tracking experience.

Map PBIs to features

When you manage a suite of products or user experiences, you might want to view the scope and progress of work across the product portfolio. You can do this by defining features and mapping PBIs to features.

Using portfolio backlogs, you can drill down from one backlog to another to view the level of detail you want. Also, you can use portfolio backlogs to view a rollup of work in progress across several teams when you setup a hierarchy of teams.

Define tasks

When your team manages their work in sprints, they can use the sprint backlog page to break down the work to be accomplished into distinct tasks.

Add a task to an item in the sprint backlog

Name the task and estimate the work it will take.

Scrum process, Task work item form

Using Scrum, teams forecast work and define tasks at the start of each sprint, and each team member completes a subset of those tasks. Tasks can include development, testing, and other kinds of work. For example, a developer can define tasks to implement PBIs, and a tester can define tasks to write and run test cases.

When teams estimate work using hours or days, they define tasks and the Remaining Work and Activity (optional) fields.

Field/tab

Usage

Indicate how many hours or days of work remain to complete a task. As work progresses, update this field. It's used to calculate capacity charts, the sprint burndown chart, and the Sprint Burndown (Scrum) report.
If you divide a task into subtasks, specify Remaining Work for the subtasks only. You can specify work in any unit of measurement your team chooses.

Select the type of activity this task represents when your team estimates sprint capacity by activity.

Track test progress

Test PBIs

From the web portal or Test Manager, you can create test cases that automatically link to a PBI or bug. Or, you can link a PBI or bug to a test case from the (links tab).

Web portal, Select the test suite and add a test case

The test case contains many fields, many of which are automated and integrated with Test Manager and the build process. For a description of each field, see Query based on build and test integration fields.

Scrum Test case work item form

The (links tab) captures the links to all the PBIs and bugs in a test case. By linking PBIs and bugs to test cases, the team can track the progress made in testing each item.

Track code defects

You can create bugs from the web portal web portal, Visual Studio, or when testing with Test Manager.

Definitions for common work tracking fields

The following fields and tabs appear in most work items. Each tab is used to track specific information, such as history, links, or attachments. These three tabs provide a history of changes, view of linked work items, and ability to view and attach files.

The only required field for all work item types is Title. When the work item is saved, the system assigns it a unique ID. The form highlights required field in yellow. For information about other fields, see Work item field index.

Field/tab

Usage

Enter a description of 255 characters or less. You can always modify the title later.

Assign the work item to the team member responsible for performing the work. Depending on the context you are working in, the drop-down menu will list only team members or contributors to the project.

When the work item is created, the State defaults to the first state in the workflow. As work progresses, update it to reflect the current state.

Use the default first. Update it when you change state. Each State is associated with a default reason.

Choose the area path associated with the product or team, or leave blank until assigned during a planning meeting.

To change the dropdown list of areas, see Add and modify area and iteration paths.

Choose the sprint or iteration in which the work is to be completed, or leave it blank and assign it later, during a planning meeting.

To change the drop-down list of iterations, see Add and modify area and iteration paths.

Review the audit trail that the system captures and capture additional information.

Every time that the work item is updated, information is appended to the history. History includes the date of the change, who made the change, and which fields were changed. You can also add formatted text to the history field.

Add all types of links, such as hyperlinks, changesets, source files, and so on.

This tab also lists all links defined for the work item.

Share more detailed information by adding files to the work item, such as email threads, documents, images, log files, or other file types.

Customize work item types

You can add fields, change the workflow, add custom rules, and add custom pages to the work item form of most work item types. You can also add custom work item types. For details, see Customize the On-premises XML process model.

Before you start tracking work, you must have a project. To create one, see Create a project.

If you have a project, start tracking work:

For more information on Agile tools:

Track impediments

Use the impediment WIT to track events that may block progress or ship a PBI. Use the Bug WIT exclusively to track code defects.

You can add an impediment from the New work item widget added to a team dashboard, or from the New menu on the Queries page.

Add work item from a New work item widget

Work items you add from the widget are automatically scoped to your team's default area and iteration paths. To change the team context, see Switch team context.

Backlog list order

The Backlog Priority field is used to track the relative ranking of PBIs, bugs, features, or epics. However, by default it doesn't appear on the work item form. The sequence of items on the backlog page is determined according to where you've added the items or moved the items on the page. As you drag items, a background process updates this field.

Work item forms displayed in a client and the web portal for TFS 2015 and earlier versions display link tabs and link control restrictions as described in the following table.

Tab name

Work item type

Link restrictions

All Links

Feedback Request

Feedback Response

  • No restrictions.

Links

Product Backlog Item

Bug

Impediment

Shared steps

Task

Test Case

  • No restrictions.

Links

Code Review Request

  • Allows only Parent and Child links to Code Review Response work items.

  • Excludes links to work items in other projects.

Stories

Feedback Response

  • Allows only Related links.

  • Allows links to Bug and Product Backlog Items.

  • Excludes links to work items in other projects.

Storyboards

Product Backlog Item

  • Allows only Storyboard links.

Tasks

Product Backlog Item

  • Allows only Child links to Tasks.

  • Excludes links to work items in other projects.

Test Cases

Product Backlog Item

Bug

  • Allows only Tested By links.

  • Allows links only to test cases.

  • Excludes links to work items in other projects.

Tested Backlog Items

Test case

  • Allows only Tests links.

  • Allows links to Bug and Product Backlog Items.

  • Excludes links to work items in other projects.