ProjectDataSet.TaskRow.TASK_CONSTRAINT_DATE Property

Specifies the constrained start or finish date, depending on the value of TASK_CONSTRAINT_TYPE.

Namespace:  [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl

Syntax

'Declaration
Public Property TASK_CONSTRAINT_DATE As DateTime
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As DateTime

value = instance.TASK_CONSTRAINT_DATE

instance.TASK_CONSTRAINT_DATE = value
public DateTime TASK_CONSTRAINT_DATE { get; set; }

Property Value

Type: System.DateTime

Remarks

If the TASK_CONSTRAINT_TYPE is set to AsLateAsPossible or AsSoonAsPossible, the value of this field is not considered.