Assignment.Replan Method (Project)
Replans the assignment by decreasing work or increasing duration.
Version Information
Version Added: Project 2010
Syntax
expression .Replan(action)
expression An expression that returns a Assignment object.
Parameters
Name |
Required/Optional |
Data Type |
Description |
---|---|---|---|
action |
Required |
PjAssignmentReplanAction |
Can be one of the following constants in PjAssignmentReplanAction: pjConstrainToMaxUnitsByDecreasingWork or pjConstrainToMaxUnitsByIncreasingDuration. |
Return Value
Nothing
Remarks
For example, if a resource calendar changes so that the resource becomes overallocated, you can replan the overallocated assignments.
Example
In he following example, an overallocated assignment selected in the Team Planner view is changed to increased duration.
ActiveCell.Assignment.Replan(pjConstrainToMaxUnitsByIncreasingDuration)