Contains the elements that define a simple work data update.
<Change>
</Change>
Attributes
Attribute |
Description |
---|---|
None |
Child Elements
ActualWork, Comments, RemainingWork, Status, StatusGuid, TotalWork |
Parent Elements
Occurrences
Minimum: 1 Maximum: 1 |
Remarks
You can define only a single Change element within each parent Assn element.
Example
The following example uses the Change element to contain a simple work data update that specifies 8 hours of actual work, 16 hours of remaining work, and 24 hours of total work for the specified assignment.
<Changes>
<Proj ID="a47faeab-0f72-455a-b629-d62faf5fece6">
<Assn ID="6c9888a8-a782-47ac-a905-e84ad1fe0fb2">
<Change>
<ActualWork>480000</ActualWork>
<RemainingWork>960000</RemainingWork>
<TotalWork>1440000</TotalWork>
</Change>