ProjectDataSet.AssignmentRow.ASSN_ACT_FINISH Property
Specifies the date and time when a task or assignment was actually completed.
Namespace: WebSvcStatusing
Assembly: ProjectServerWebServices (in ProjectServerWebServices.dll)
Syntax
'Declaration
Public Property ASSN_ACT_FINISH As DateTime
Get
Set
'Usage
Dim instance As ProjectDataSet.AssignmentRow
Dim value As DateTime
value = instance.ASSN_ACT_FINISH
instance.ASSN_ACT_FINISH = value
public DateTime ASSN_ACT_FINISH { get; set; }
Property Value
Type: System.DateTime
Remarks
ASSN_ACT_FINISH can be set manually, or it can be generated by Microsoft Office Project. If it is generated by Project, it is set to the date when ASSN_PCT_WORK_COMPLETE is set to zero (0).
See Also
Reference
ProjectDataSet.AssignmentRow Class