ProjectDataSet.TaskRow.TASK_LATE_FINISH Property
Contains the latest date that a task can finish without delaying the finish of the project.
Namespace: WebSvcStatusing
Assembly: ProjectServerWebServices (in ProjectServerWebServices.dll)
Syntax
'Declaration
Public Property TASK_LATE_FINISH As DateTime
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As DateTime
value = instance.TASK_LATE_FINISH
instance.TASK_LATE_FINISH = value
public DateTime TASK_LATE_FINISH { get; set; }
Property Value
Type: System.DateTime
Remarks
Read-only. TASK_LATE_FINISH is based on the task's late start date, as well as the late start and late finish dates of predecessor and successor tasks, and other constraints.