ProjectDataSet.TaskRow.TASK_PCT_COMP Property

Task percent complete is percentage of elapsed duration compared with the remaining duration.

Namespace:  WebSvcStatusing
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

Syntax

'Declaration
Public Property TASK_PCT_COMP As Integer
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Integer

value = instance.TASK_PCT_COMP

instance.TASK_PCT_COMP = value
public int TASK_PCT_COMP { get; set; }

Property Value

Type: System.Int32

Remarks

Read-only. TASK_PCT_COMP = (TASK_ACT_DUR / TASK_DUR) * 100

When a task is created, the percent complete is zero. TASK_PCT_COMP is calculated when you enter actual duration, remaining duration, or actual work (which affects actual duration).

If the % Complete field is set to a value greater than zero, the Actual Start field is set to the scheduled start date if you have not yet entered an actual start date. If the % Complete field is set to 100, the Actual Finish field is set to the scheduled finish date.

If you type a value in the % Complete field, Project automatically calculates actual duration and remaining duration. Likewise, entering a value in the Actual Duration or Remaining Duration field automatically recalculates the other fields.

See Also

Reference

ProjectDataSet.TaskRow Class

ProjectDataSet.TaskRow Members

WebSvcStatusing Namespace