ProjectDataSet.TaskRow.TASK_PRIORITY Property

Task priority is the level of importance given to a task, which indicates how readily a task or assignment can be delayed or split during resource leveling.

Namespace:  WebSvcStatusing
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

Syntax

'Declaration
Public Property TASK_PRIORITY As Integer
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Integer

value = instance.TASK_PRIORITY

instance.TASK_PRIORITY = value
public int TASK_PRIORITY { get; set; }

Property Value

Type: System.Int32

Remarks

Priority levels range from 0 through 1000. The lowest priority is 0. The default priority is 500.

See Also

Reference

ProjectDataSet.TaskRow Class

ProjectDataSet.TaskRow Members

WebSvcStatusing Namespace