ProjectDataSet.TaskRow.TASK_FIXED_COST_ACCRUAL Property

Fixed cost accrual indicator indicates how fixed costs are to be accrued in a task.

Namespace:  WebSvcStatusing
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

Syntax

'Declaration
Public Property TASK_FIXED_COST_ACCRUAL As Short
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Short

value = instance.TASK_FIXED_COST_ACCRUAL

instance.TASK_FIXED_COST_ACCRUAL = value
public short TASK_FIXED_COST_ACCRUAL { get; set; }

Property Value

Type: System.Int16

Remarks

  • 1 = Start; costs are accrued as soon as the task starts, as indicated by a date entered in the ActualStart field.

  • 2 = End; costs are not incurred until remaining work is zero.

  • 3 = Pro-rated (default); costs accrue as work is scheduled to occur and as actual work is reported.