ProjectDataSet.TaskRow.TASK_FIXED_COST_ACCRUAL Property
Fixed cost accrual indicator indicates how fixed costs are to be accrued in a task.
Namespace: WebSvcStatusing
Assembly: ProjectServerWebServices (in ProjectServerWebServices.dll)
Syntax
'Declaration
Public Property TASK_FIXED_COST_ACCRUAL As Short
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Short
value = instance.TASK_FIXED_COST_ACCRUAL
instance.TASK_FIXED_COST_ACCRUAL = value
public short TASK_FIXED_COST_ACCRUAL { get; set; }
Property Value
Type: System.Int16
Remarks
1 = Start; costs are accrued as soon as the task starts, as indicated by a date entered in the ActualStart field.
2 = End; costs are not incurred until remaining work is zero.
3 = Pro-rated (default); costs accrue as work is scheduled to occur and as actual work is reported.