ProjectDataSet.ProjectRow.PROJ_OPT_SPLIT_IN_PROGRESS Property
Indicates whether to split tasks that are in progress.
Namespace: WebSvcStatusing
Assembly: ProjectServerWebServices (in ProjectServerWebServices.dll)
Syntax
'Declaration
Public Property PROJ_OPT_SPLIT_IN_PROGRESS As Boolean
Get
Set
'Usage
Dim instance As ProjectDataSet.ProjectRow
Dim value As Boolean
value = instance.PROJ_OPT_SPLIT_IN_PROGRESS
instance.PROJ_OPT_SPLIT_IN_PROGRESS = value
public bool PROJ_OPT_SPLIT_IN_PROGRESS { get; set; }
Property Value
Type: System.Boolean
true if in-progress tasks can be split.
Remarks
PROJ_OPT_SPLIT_IN_PROGRESS maps to the Split in-progress option in the Schedule tab of the Options dialog box in Microsoft Office Project Professional.
The default value for new projects is determined by the enterprise global template. If there is no enterprise global template value, the default value is true.