NewTaskStartDate Element

This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.

Specifies whether the default start date for a new task is the project start date or the current date.

<NewTaskStartDate>
  IntegerValue
</NewTaskStartDate>

Parent Elements

Project

Occurrences

Minimum: 0

Maximum: 1

Text Value

Required Integer

Value

Description

0

Project start date

1

Current date

See Also

Concepts

Project Elements and XML Structure

XML Schema for the Project Element