TotalSlack Element

This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.

The amount of time a task can be delayed without delaying a project's finish date. Time is in tenths of a minute.

<TotalSlack>
  IntegerValue
</TotalSlack>

Parent Elements

Task

Occurrences

Minimum: 0

Maximum: 1

Example

The following example shows a task can be delayed by two days, if the work day is eight hours (2 days x 8 hours/day x 60 minutes/hour x 10 tenths/minute = 9600 tenths). The actual slack time available in this case is the same as the total slack.

<Task>
   . . .
   <FreeSlack>9600</FreeSlack>
   <TotalSlack>9600</TotalSlack>
   . . .
</Task>