ActualCost Element

This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.

For a Task, ActualCost is the costs incurred for work already performed by all resources on a task, along with any other recorded costs associated with the task.

For a Resource, it is the sum of costs incurred for the work already performed by a resource for all assigned tasks.

For an Assignment, it is the cost incurred for work already performed by a resource on a task.

<ActualCost>
  DecimalValue
</ActualCost>

Parent Elements

TaskResourceAssignment

Occurrences

Minimum: 0

Maximum: 1

See Also

Concepts

Task Elements and XML Structure

XML Schema for the Tasks Element

Resource Elements and XML Structure

XML Schema for the Resources Element

Assignment Elements and XML Structure

XML Schema for the Assignments Element