Change Element (SetAssignmentWorkData)
This content is outdated and is no longer being maintained. It is provided as a courtesy for individuals who are still using these technologies. This page may contain URLs that were valid when originally published, but now link to sites or pages that no longer exist.
Contains the elements that define a simple work data update.
<Change>
</Change>
Attributes
Attribute |
Description |
---|---|
None |
Child Elements
ActualWork, Comments, RemainingWork, Status, StatusGuid, TotalWork |
Parent Elements
Occurrences
Minimum: 1 Maximum: 1 |
Remarks
You can define only a single Change element within each parent Assn element.
Example
The following example uses the Change element to contain a simple work data update that specifies 8 hours of actual work, 16 hours of remaining work, and 24 hours of total work for the specified assignment.
<Changes>
<Proj ID="a47faeab-0f72-455a-b629-d62faf5fece6">
<Assn ID="6c9888a8-a782-47ac-a905-e84ad1fe0fb2">
<Change>
<ActualWork>480000</ActualWork>
<RemainingWork>960000</RemainingWork>
<TotalWork>1440000</TotalWork>
</Change>
</Assn>
</Proj>
</Changes>