Application.ProjectBeforeTaskNew Event
Project Developer Reference |
Occurs before one or more tasks are created.
Syntax
expression.ProjectBeforeTaskNew(pj, Cancel)
expression A variable that represents an Application object.
Parameters
Name | Required/Optional | Data Type | Description |
---|---|---|---|
pj | Required | Project | The project in which a task or tasks are being created. |
Cancel | Required | Boolean | False when the event occurs. If the event procedure sets this argument to True, the new task or tasks are not created. |
Return Value
nothing
Remarks
Project events do not occur when the project is embedded in another document or application.
The ProjectBeforeTaskNew event doesn't occur when data is merged or appended into a project, during resource pool operations, when inserting or removing a subproject, or when changes have been made using a custom form.
See Also