PJTaskOutlineShowLevel Enumeration

Project Developer Reference

Constant specifying the task outline levels to display.

Requirements

Name Value Description
pjTaskOutlineShowLevel1 1 Display level 1.
pjTaskOutlineShowLevel2 2 Display levels 1 and 2.
pjTaskOutlineShowLevel3 3 Display levels 1 through 3.
pjTaskOutlineShowLevel4 4 Display levels 1 through 4.
pjTaskOutlineShowLevel5 5 Display levels 1 through 5.
pjTaskOutlineShowLevel6 6 Display levels 1 through 6.
pjTaskOutlineShowLevel7 7 Display levels 1 through 7.
pjTaskOutlineShowLevel8 8 Display levels 1 through 8.
pjTaskOutlineShowLevel9 9 Display levels 1 through 9.
pjTaskOutlineShowLevelMax 65535 Display all levels.