PjTaskLinkType Enumeration
Project Developer Reference |
Constant specifying the type of links between tasks.
Requirements
Name | Value | Description |
---|---|---|
pjFinishToFinish | 0 | Link tasks from finish to finish. |
pjFinishToStart | 1 | Link tasks from finish to start. |
pjStartToFinish | 2 | Link tasks from start to finish. |
pjStartToStart | 3 | Link tasks from start to start. |