Syntax
expression.UpdateTasks(PercentComplete, ActualDuration, RemainingDuration, ActualStart, ActualFinish, Notes)
expression A variable that represents an Application object.
Parameters
Name | Required/Optional | Data Type | Description |
---|---|---|---|
PercentComplete | Optional | Variant | The percent complete of the active tasks. |
ActualDuration | Optional | Variant | . The actual duration of the active tasks. |
RemainingDuration | Optional | Variant | The remaining duration of the active tasks. |
ActualStart | Optional | Variant | The actual start date of the active tasks. |
ActualFinish | Optional | Variant | The actual finish date of the active tasks. |
Notes | Optional | String | Any comments for the active tasks. |
Return Value
Boolean
Remarks
Using the UpdateTasks method without specifying any arguments displays the Update Tasks dialog box.
Example
The following example first creates a new task called "TestTask-1" and updates the task to 50% complete. Then it deletes the task.