Application.DateAdd Method
Project Developer Reference |
Adds a duration to a date to return a new date.
Syntax
expression.DateAdd(StartDate, Duration, Calendar)
expression A variable that represents an Application object.
Parameters
Name | Required/Optional | Data Type | Description |
---|---|---|---|
StartDate | Required | Variant | The original date to which the duration is added. |
Duration | Required | Variant | The duration to add to the start date. |
Calendar | Optional | Object | A resource, task, or base calendar object. The default value is the calendar of the active project. |
Return Value
Variant
Example
The following example displays the finish date of a three-day task that begins on 7/11/07 at 8 A.M.
Visual Basic for Applications |
---|
|