TaskDependency Object
Project Developer Reference |
Represents the link type and link lag information between two tasks. The TaskDependency object is a member of the TaskDependencies collection.
Using the TaskDependency Object
Use TaskDependencies(Index), where Index is the dependency index, to return a single TaskDependency object. The following example adds 1.5 days of lag to the link between the specified task and the predecessor specified in its first task dependency.
|
Using the TaskDependencies Collection
Use the TaskDependencies property to return a TaskDependencies collection. The following example examines each predecessor for the specified task and displays a message for each that has a priority of "High" or better.
|
Use the Add method to add a TaskDependency object to the TaskDependencies collection. The following example links "Preliminary Research & Approval" as a predecessor to "Draft Initial Business Case" in a finish-to-start relationship.
|