Application.DateSubtract Method
Project Developer Reference |
Returns the date that precedes another date by a specified duration.
Syntax
expression.DateSubtract(FinishDate, Duration, Calendar)
expression A variable that represents an Application object.
Parameters
Name | Required/Optional | Data Type | Description |
---|---|---|---|
FinishDate | Required | Variant | The date used as the end of the duration. |
Duration | Required | Variant | The duration to subtract from the finish date. |
Calendar | Optional | Object | A resource, task, or base calendar object. The default value is the calendar of the active project. |
Return Value
Variant
Example
The following example displays the start date of a task that lasts three days and ends on 7/13/02 at 5:00 P.M.
Visual Basic for Applications |
---|
|
See Also