Task.Calendar Property
Project Developer Reference |
Returns or sets the calendar to be used when scheduling the task. Read/write String.
Syntax
expression.Calendar
expression A variable that represents a Task object.
Return Value
String
Remarks
The Calendar property does not return any meaningful information for material resources. Setting a value returns a trappable error (error code 1101) when applied to material resources.
Example
The following example resets the calendar for the active project.
Visual Basic for Applications |
---|
|