<AccrueAt> Element

Indicates how and when resource standard and overtime costs are to be charged, or accrued, to the cost of a task

Element Properties

Property Value
Data Type Integer
 
1 Start; costs are accrued as soon as the task starts, as indicated by a date entered in the ActualStart field.
2 End; costs are not incurred until remaining work is zero.
3 Pro-rated (default); costs accrue as work is scheduled to occur and as actual work is reported.
Minimum Occurrences 0
Maximum Occurrences 1
Default Value N/A
Abstract False
Nillable False
Element Constraints N/A

Parent Elements

Resource

See Also

XML Schema for the <Resource> Element
XML Structure for the <Resource> Element