ProjectDataSet.TaskRow.TASK_LEVELING_CAN_SPLIT Property
Task leveling can split indicates whether the resource leveling function can cause splits on remaining work on this task.
Namespace: WebSvcProject
Assembly: ProjectServerWebServices (in ProjectServerWebServices.dll)
Syntax
'Declaration
Public Property TASK_LEVELING_CAN_SPLIT As Boolean
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Boolean
value = instance.TASK_LEVELING_CAN_SPLIT
instance.TASK_LEVELING_CAN_SPLIT = value
public bool TASK_LEVELING_CAN_SPLIT { get; set; }
Property Value
Type: System.Boolean
Remarks
If TASK_LEVELING_CAN_SPLIT is set to true, leveling can interrupt the task. If this field is set to false, leveling cannot split the task.