Tracking changes in Project 2007
I apologize to readers for the delay in posting a new topic. The last few weeks have been busy for us in the product team as we start to get our Beta 2 build completed. The release will be in late spring and I’ll have a dedicated post on how that will work, for those interested in learning more. I have received a couple of questions about it but the details are still not finalized.
This week I would like to show you two new features we have introduced in Project 2007 that will improve Project Managers’ productivity by giving you the ability to efficiently see how changes you make effect the rest of the project plan. In addition, Project 2007 gives you the ability to see what’s driving a task. That is, for example, if you want to understand why a task has pushed out the schedule, you easily can.
Change Highlighting
Project 2007 provides you with an option to view how the changes you make to the schedule impact the rest of the project. Change Highlighting illustrates all that is impacted by your change.
In the example below, I am using one of the new Project templates we are shipping with Project 2007, “Strategic Merger or Acquisition Evaluation”.
I changed task 17 ‘Define Selection Scenario…’ to have duration of ‘4 days’. After changing the duration value, everything that also changed as a result of my extension of the task duration got highlighted: the finish date for my task, the following task that dependent on task 17, the inner and outer milestone summary tasks.
This feature gives you incredible power to validate the change and helps you answer questions that were harder to answer before: Did this change cause a schedule slip? What other tasks will get impacted by the change? Should I make the change?
The highlighting will persist until you make another change or save the project. Since Project 2007 offers multiple levels of undo, you can use both features combined to do many “What-if” scenario analysis with your projects.
Task Drivers
Another question you may be faced with when reviewing your project schedule may be what is causing my task to be scheduled when it is as opposed to on an ealier date? This can be especially problematic if you are managing a project with thousands of tasks. You may end up spending hours trying to trace back the dependencies, review resource availability, calendars etc. Project 2007 now does the work for you! When you select a task, you can select to view the Task Drivers pane and the information that you need to find out what is driving that task is displayed to you on a pane on the left of the project. You can easily turn on this pane by selecting the ‘Task Driver’ option on the Project menu (new in Project 2007).
I am using the same project I used above. Once I opened the ‘Task Driver’ pane for task 17, I get all the information I need to see “what are the factors causing the task to start when it is”. In addition to predecessor tasks, you also get a link to the calendar of the resource(s) assigned to the task. This is very helpful if your task is being delayed due to the resource being on vacation.
Both Change Highlighting and Task Drivers will be the first couple of new features you will immediately notice in Project 2007 and that I personally have become dependant on for my projects.
The screen shots I used are from our latest build but since the product is still the Beta phase there may be some changes to the final version.
Comments
- Anonymous
April 10, 2006
Hello,
I thought you might be able to provide the very basic knowledge about if one can use MS Project software
with Mac users? I want to use this software to help manage a project for business using all MACS.
Thanks
Anna
415-664-4051
aadea@sbcglobal.net - Anonymous
April 10, 2006
Hi Anna -
We don't have a version of Project available for MACs. You could look into using Virtual PC though this is not a configuration that we haven't tested ourselves (and I know the performance can be a problem).
If you would like to use Project Server, then the Project web access that your team members would use is supported but the Project Managers of your organization would still require to run Project Professional from a PC environment.
Lidiane - Anonymous
April 12, 2006
Is there any changes in risk management in the project 2007? - Anonymous
April 13, 2006
Alex -
Are you referring to Project Professional with the Server? Assuming it is, Project Server 2007 is completely built on Windows SharePoint Services (WSS) technology which enabled us to build a very well integrated Risks, Issues and Commitments solution. And all of this is accessible from Project Professional.
For example, you can define a risk that's caused by a task on one of your projects. Once you define that, you can assign this risk to a resource and he/she will get notified of that on their homepage view. The risks, issues and commitments will be integrated into the Project workspace as well, so everyone who has access to that will be able to keep track and be informed of the risks, issues and commitments. Also, all of this data will be available on the Project reporting database and OLAP cubes. So, management will be able to analyze trends across project, evaluate resource overload, etc.
I hope this answers your question. This is a great topic! I'll plan to have a future post on this.
Thanks,
Lidiane - Anonymous
June 28, 2006
The comment has been removed - Anonymous
August 09, 2006
The comment has been removed - Anonymous
November 21, 2006
Hi I am having 2 issues:
- When I update the % complete of a subtask the roll up task % complete is not updating.
- When I change the date or duration of a subtask or a dependent task the dependency does not move out and the roll up task date does not change? Am I missing something? Thanks Donna
- Anonymous
May 22, 2007
hi, i m learning to use the software at university. 1.Can you give me an exact definition of tracking? i know how to track.
- What are some of the screens that help summarise a project apart from the Statistics from the project information.
Anonymous
September 14, 2007
Hi - I am managing multiple projects and having difficulting keeping track of when I last published updates to a schedule. Is there any way to see the last published date?Anonymous
February 11, 2009
Please aehm, someoane answered you about Is there any way to see the last published date?Anonymous
October 13, 2009
Is there a "field" that captures the date the change was made so you can track progress. For example, if a change was made yesterday and a given task went from 30% to 50% complete, is there a field showing the 20% increase since yesterday or a field that captures that yesterday a change was made. Thank you, JasonAnonymous
April 04, 2011
i am looking for tracking in 2010 which is in the tools menu in 2007Anonymous
February 01, 2012
Is there any way that one can access the list of changed Tasks/Fields from a program / add-in?