My Tasks Page and Colored Lines
You launch the My Tasks page in Project Server 2007 and you see these colored lines next to your tasks. The first thing that comes to mind is what do they mean?
Below is the key to these colors. Please bear in mind that these colors are meant as guidance and are subject to the influence of pending approvals and updates.
- Green - This indicates a New Task
- Yellow/Orange - This task will be due soon. Orange will be due sooner than Yellow
- Red - Overdue/Past the due date.
Lastly, a pink background on the finish date denotes that it is past today's date.
Technorati Tags: Microsoft Project,Project Management Software,Microsoft Project Server,MS Project,MS Project Server,Tasks
Comments
Anonymous
December 21, 2007
The comment has been removedAnonymous
December 21, 2007
Interesting point at blogs.msdn.comAnonymous
November 12, 2008
The comment has been removedAnonymous
November 25, 2008
The comment has been removed