Material Resource Usage Illustrated
Dr. Ed Hanna, one of our most senior field people for EPM recently posted a great example of using material resources using Project Server. So, I'm taking Ed's e-mail and converting into this post. I hope you find this very useful.
Here's an example of how you might use Project to track the pouring of the concrete for one section of a dam.
First, create a Resource Sheet entry for the concrete. Click the image below for more detail.
The dam footing work we are tracking will contain 20,000 cu. meters of concrete and will be poured over a ten workday period. The Gantt Chart task to pour this footing looks as follows.
Next, the Resource Usage view shows the planned usage of concrete at 2,000 cu. meters per day. Note: there is no Actual Work as the task has not yet begun.
Once progress begins, the Resource Usage view can be used to report actual usage. In this case, only 1,000 cu. meters of concrete poured on day #1. Consequently, work is off to a slow start.
Here’s the full Resource Usage view showing 3,000 cu. meters of additional concrete poured on day #2. On the left you can see totals. For example, you can see that 20,000 cu. meters of concrete is scheduled to be poured (i.e. Work) and so far 4,000 cu. meters have been poured (i.e. Actual Work). The graph in the lower portion of the display shows Cumulative Scheduled Work (i.e. the cumulative amount of concrete scheduled to be poured).
The display can also be changed to track the cost of the concrete. The graph in the lower portion of the display shows Cumulative Scheduled Cost (i.e. the cumulative cost of concrete scheduled to be poured).
I hope this is helpful. By the way, Hoover Dam contains 3.33M cu. meters of concrete.
Technorati tags: Project Management, Project Server 2007, Material Resources, Project 2007, Project Professional 2007
del.icio.us tags: Project Management, Project Server 2007, Material Resources, Project 2007, Project Professional 2007
Comments
Anonymous
February 19, 2007
How can I change a date and everything follows (date change)Anonymous
May 06, 2007
Please inform me if some one can put Engineer,Foreman,Labour, Equipment, Material, and also the cost breakdown, any body can help thanks My e-mail>>> Khadafi_97@yahoo.co.idAnonymous
May 25, 2007
<a href= http://www.mybbland.com/?mforum=lexaprosidef >lexapro withdrawl</a> http://www.phpbbserver.com/lexici/ lexapro effectsAnonymous
May 25, 2007
<a href= http://www.rodiary.com/produrano/ >does propecia work</a> http://www.pianetablog.com/valiumsideeffects/ presrition valiumAnonymous
May 25, 2007
<a href= http://www.pianetablog.com/valiumnoprescription/ >valium and purchase</a> http://www.pianetablog.com/wellbutrinzol/ wellbutrin pricesAnonymous
May 26, 2007
<a href= http://zocorprices.jconserv.net/ >zocor withdrawal effect</a> http://acyclovirsi.phpbb3.com/ acyclovir to treat fluAnonymous
May 27, 2007
<a href= http://justblogme.com/lamisilskincream/ >lamisil digger pics</a> http://justblogme.com/levaquindosagee/ levaquin tabletsAnonymous
May 28, 2007
<a href= http://whatisamoxicillin.blog.hr/ >dug interactions amoxicillin</a> http://whatisativan.blogyx.com/ ativan doseAnonymous
May 28, 2007
The comment has been removedAnonymous
May 28, 2007
<a href= http://codeinesy.diaryland.com/ >robutussen with codeine</a> http://diazepamsideeffects.alkablog.com/ diazepam overnightAnonymous
May 28, 2007
<a href= http://flexerilweight.blogtopia.com/ >flexeril hand pain</a> http://ultracetovernight.mjblog.pl/ ultracet vs vicodinAnonymous
May 28, 2007
<a href= http://ultracetovernight.mjblog.pl/ >all about ultracet</a> http://www.beepworld.it/members/valtrexshin/ valtrex australia cfsAnonymous
May 28, 2007
<a href= http://www.beepworld.it/members/valtrexshin/ >valtrex wav file</a> http://s7.invisionfree.com/xenicalforum/ xenical overnightAnonymous
March 09, 2009
It is very useful. My concern is about the stock. Is it possible to have this functionality? I suppose you know what I mean. The system could track the amount of material available. If you don’t have enough you could have a “overallocation” problem like working with a human resource.Anonymous
March 12, 2009
You could do this through custom fields. Add a custom resource number field which would store the number of stock you have. Then you could compare this to the work field which shows the current number of units you plan to use for that material resource. You could even add another custom field that would use a graphical indicator that would turn red when work is greater than stock. Thanks.Anonymous
August 08, 2009
I am trying this example but I am not getting same results as shown in the article. Can some one upload or provide link to download MPP file that shows this example? It will be great help.. Regards JackAnonymous
June 04, 2010
Here's a video on material resourcesAnonymous
June 04, 2010
Whoops, I forgot to add the link to the video from Office.com office2010.microsoft.com/.../video-create-material-resources-in-your-project-VA101861630.aspxAnonymous
June 07, 2010
Thanks for your very useful topic. May i ask you if we could add or create another fields of usage details in Detail Styles section ? regards henryAnonymous
April 07, 2011
ONE OF THE BEST BLOGS SHOWING RESOURCES CONCEPT IN MS PROJECT FOR BEGINNERS