Administrative Time Explained

It’s time again for another posting from me, David Ducolon, on some best practice use of Project Server. This time I will go in depth about the Administrative Time feature in Project Server 2007.

Before I tell you about what 2007 has to offer and how best to implement and use it, I feel I must first tell you about the history of this feature area. 

  • In 2002, we introduced a server feature for tracking time on other commitments than just project assignments. This was implemented with “Project Calendar Exceptions” through a process where the team member sent a request to another individual, who had the permissions to edit resource details. This individual then applied the calendar exception to the checked out resource pool. The enterprise resource pool would then be opened and saved from Project Professional before it would be reflected back on the servers’ resource availability information. This addressed the need for customers but for some it was slightly cumbersome. An additional request from customers was to be able to report on this data. That was seen as a must do item for the next version of Project Server.
  • In 2003, the next version after 2002 was released. In 2003 we altered this feature and called it “Non Project Time”. The change was significant in that resources needed to be assigned to a special type of project called an “Administrative” project. Calendar exceptions were not an object customers can report on. This allowed full reporting on the time commitments for resources assigned to other non project work. The process was more streamlined with the removal of the enterprise resource pool update. However a publish of the administrative project was still necessary before the time request would be available for viewing in Project Server.

So with the experiences of 2002 and 2003, we took a long hard look at this feature for 2007. I am happy and proud to announce that in 2007, the process was further streamlined, the architecture was extremely scalable, performance out does previous versions and the category type and behavior is fully customizable to meet your needs for planning, tracking and reporting on work other than project assignments.

The functionality is so dramatically different that we changed the name to “Administrative Time”. The setup work requires:

    1. Customers to create Administrative Categories
    2. Each category must be marked as “Work” or “Non Work”
  1.      i) Non Working Time – Time scheduled as project calendar exceptions directly from the user without the need to involve Project Professional.  While it still blocks the Project scheduling engine from assigning work to the individual during that time.

          ii) Working Time – Time scheduled as virtual task assignments.  These are virtual, since they do not reside in any true project file, instead they are simple records in the SQL database.  This has the effect of allowing resources to be scheduled in excess of 100%.

    1. Optionally categories can be set to require a manager’s approval
    2. Optionally categories may be marked for “Always Display” which places a copy of that category on every timesheet that is used

Customers may create as many “categories” as they want without any impact on performance or scalability.

Simple Example for Managing Administrative Time Categories

Simple View for managing Administrative Categores 

Categories may be renamed, but they cannot be deleted once they have been saved to the database. This preserves the integrity of timesheets. If the category is no longer applicable you must close the category’s status and it will no longer be available to users without disrupting the integrity of the historical timesheets.

HOW TO USE

Let’s now talk about how best to implement and use these options. To begin with I would like you to consider the term “Non Working” and “Working” as terms that mean “Block Scheduling” and “Allow Over Allocation” respectively. With that understood, the first rule to consider is:

Non Working work type should only be used on administrative categories that will be used to plan time off.  

This is important since Project does not like to move actual work once established and calendar exceptions cannot allow work to exist during time periods which they are set to occupy.  An example of what you should NOT do is as follows: 

     i) You create a category called “Sick time” and make that non working. 

     ii) A member of your team comes to work on Monday and works on a task that begins on Monday and goes for two days. 

     iii) The team member reports that the task is 50% complete.  But then the employee goes home sick. 

     iv) At the end of the week the team member fills in his timesheet and reports 4 hours of sick time on Monday. 

Result: Project took the 16 hour task and assigned 50% of the work as actual work reported by the team member on Monday.  But the timesheet also wants to place a calendar exception for that day.  The team member should only have been able to logically complete 25% of the work on the task.  Below are screen shots of what happens:

16 hours of work on Wednesday and Thursday, auto imported from My Tasks, with 8 hours of “Dr. Appointment” (non working time) entered into the timesheet.

image

After the timesheet is saved, the calendar exception is created.  As you can see the assignment to task “Plan 1”  seems to have lost the 8 hours of work on Wednesday (2/4).  But the total work is still at 2 days with only 8 hours of actual work.  This presents a difficult situation for Project to understand.

image

If all of your calendars and time settings are set to 8 hours for the definition of a day, after a round trip through project all will be fine.  However if either the project or resource calendar or PWA setting of a day is not 8 hours, the results will be to reduce the work and to apply 8 hours of non working time.

Solution:

To avoid this situation I strongly encourage all customers to be very careful when creating an Administrative time category with a Working Type setting of “non working”.   Personally I set my server to break “sick” time into two categories. 

1. I re-label the standard “Sick” category to “Dr. Appointment” and

2. I create a new category called “Illness” and set the working type option to “working”.

I would expect employees to plan for Doctor related absences in the future or before submitting actual work; which is really the problem.  And Illnesses would conversely be submitted after returning to work when it would be reasonable and somewhat common to report the hours away from work after entering actual work possibly on the same day.

This will allow the resource to be overscheduled for Illnesses which will not automatically slip the project schedule and allow planned absences to be entered while not allowing the resource to be overscheduled and if initially planned then the task will slip accordingly.

I hope this has been enlightening and useful.  If you find any particular aspect of Project Server that you wish to have explained with best practices feel free to drop a comment on this blog and you may see your suggestion in a future best practice update.

Comments

  • Anonymous
    February 18, 2009
    Thanks David. Would you know how time recorded in the admin time categories can be reported on through cubes or by querying the reproting DB through an SSRS report? For example, we might be interested in knowing how many sick days have been taken over a period of time?

  • Anonymous
    March 04, 2009
    Eureka. That makes sense - thanks for the blog

  • Anonymous
    March 04, 2009
    The comment has been removed

  • Anonymous
    March 18, 2009
    Hi David, Where we can find actual work per resources per day. In what table. Could you advise. Thanks before.

  • Anonymous
    March 25, 2009
    My client has a vacation calendar that contains all the vacation time for individuals in the organization. I want to transition this to Project Server which works well for having staff request their vacation days by entering and allowing workflow to route to their supervisor. My question is: How do I make this vacation calendar viewable by all staff so that if you want to see when an individual is scheduled for vacation or who is on vacation for a specific day you can see that? Thanks

  • Anonymous
    April 04, 2009
    Hi David, I have an issue with Admin time and was wondering if you could give me your view? Project Server was set up with timesheets and users were suppose to report updates on a daily basis. After a while we realised that this wasn't fitting our business and so decided to switch to weekly updates. I changed the Server Settings of Timesheets to have weekly updates. This worked fine for task updates. However once I made this change the admin time fields seem to lock and I couldn't diretly enter admin time into the grid. I have to add admin time by the planning dialogue. Is this standard functionality? As soon as I switch back to daily (i.e. a 7 day grid) I can add admin time directly into the grid again. All information in books and online seem to be related to having updates daily, no once has documented a weekly timesheet. Cheers Bob

  • Anonymous
    April 06, 2009
    The comment has been removed

  • Anonymous
    May 20, 2009
    Is there a way to create an overview (preferably in the Resource Assignments view) of the Administrative time. I need to have a complete overview of working and non-working hours. Thanks in advance.

  • Anonymous
    June 02, 2009
    Sir, Before you add any more features, PLEASE go get the basic functionality working. One of my biggest gripes with Project is that task names disappear between save/open cycles. When a task group is collapsed, sometimes the next time I open the file and un-collapse (ie expand) the tasks, THEY ARE BLANK. All the dates and resources, etc.. are there, but the NAMES ARE ALL BLANK. So, I have to go to an old version, and copy back all the names, checking one by one that I account for row deletions, additions. Over and over.. GET THE BASIC FUNCTIONALITY WORKING. No one uses Project because they love it, we use it because we must at work; hence the extraordinary frustration you read about every day.. This example was only one of many basic functionality items that does not work reliably.

  • Anonymous
    July 15, 2009
    Is there a way to have a specific category always display for individual users timesheets instead of all users timesheets?

  • Anonymous
    July 27, 2009
    We are testing Planned Admin Time and when type a description when requesting the time, the description comes up blank when the manager views the request for approval.  When the requestor goes back in, the description is still there....just the manager can't see it.  We want to use this as a communication that the requestor has gotten required approval.  Any suggestions? thanks

  • Anonymous
    July 30, 2009
    My client has a vacation calendar that contains all the vacation time for individuals in the organization. I want to transition this to Project Server which works well for having staff request their vacation days by entering and allowing workflow to route to their supervisor. My question is: How do I make this vacation calendar viewable by all staff so that if you want to see when an individual is scheduled for vacation or who is on vacation for a specific day you can see that?

  • Anonymous
    September 21, 2009
    Hi, We are using Project Server 2007. After creating the relevant timesheets and some administrative categories, I entereded in one of my timesheets for one of the days "8h" at "Vacancy", which is defined as Status = open, Work Type = Non Work, Approve = Yes and Always Display selected. At first, I clicked on "Save" and as a result, the green bullit at Vacancy turned to yellow (right). Then, I clicked on "Save and Submit" and as a result the message in red appears: "The submitted timesheet contains lines which either are pending approval or have been rejected. You must either delete these lines from your timesheet or obtain approvals and resubmit." (right). When I turned to the user which is the Timesheet manager for this resource, I saw the approval request for "Vacancy" with "0h". I originally requested 8h vacancy. Why has this value turned to zero instead of 8 hours? When the Timesheet manager approves the vacancy request, my timesheet shows the correct 8h Vacancy with the green status. Does anyone know why the approval request showed 0 hours instead of 8 hours? Many thanks in advance!