Udostępnij za pośrednictwem


Delete timesheets (Project Server 2010)

 

Applies to: Project Server 2010

Topic Last Modified: 2012-08-22

When a timesheet is no longer needed, you can delete it from Microsoft Project Server 2010. Note that this process deletes the timesheet completely from Project Server and it cannot be retrieved.

Use the following procedure to delete timesheets from Project Server.

To delete timesheets

  1. On the PWA home page, click Server Settings.

  2. On the Server Settings page, in the Database Administration section, click Delete Enterprise Objects.

  3. On the Delete Enterprise Objects page, select the Timesheets option.

  4. Select the range of timesheet end dates that you want to delete.

  5. Click Delete.

See Also

Other Resources

TimeSheet.QueueDeleteTimesheet Method