Returns the number of whole working days between start_date and end_date. Working days exclude weekends and any dates identified in holidays. Use NetworkDays to calculate employee benefits that accrue based on the number of days worked during a specific term.

public double NetworkDays (object Arg1, object Arg2, object Arg3);
Public Function NetworkDays (Arg1 As Object, Arg2 As Object, Optional Arg3 As Object) As Double

Parameters

Arg1
Object

Start_date - a date that represents the start date.

Arg2
Object

End_date - a date that represents the end date.

Arg3
Object

Holidays - an optional range of one or more dates to exclude from the working calendar, such as state and federal holidays and floating holidays. The list can be either a range of cells that contains the dates or an array constant of the serial numbers that represent the dates.

Returns

Remarks

Important: Dates should be entered by using the DATE function, or as results of other formulas or functions. For example, use DATE(2008,5,23) for the 23rd day of May, 2008. Problems can occur if dates are entered as text.

Microsoft Excel stores dates as sequential serial numbers so they can be used in calculations. By default, January 1, 1900 is serial number 1, and January 1, 2008 is serial number 39448 because it is 39,448 days after January 1, 1900. Microsoft Excel for the Macintosh uses a different date system as its default.

If any argument is not a valid date, NetworkDays returns the #VALUE! error value.