다음을 통해 공유


Example: Use reduction keys

Important

This content is archived and is not being updated. For the latest documentation, see Microsoft Dynamics 365 product documentation. For the latest release plans, see Dynamics 365 and Microsoft Power Platform release plans.

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

You can use a reduction key to define how to reduce forecast requirements. Here are some examples that show how to set up a reduction key, the different reduction key settings, and the results.

Example 1

Using the forecast reduction principle Percent - reduction key

This example shows how a reduction key reduces demand forecast requirements according to the percentages and periods that are defined by the reduction key. Set up the following lines in the Reduction keys form:

Change

Unit

Percent

1

Month

100

2

Month

75

3

Month

50

4

Month

25

  • Link the reduction key to the item's coverage group.

  • Select Percent - reduction key in the Reduction principle field in the Master plans form.

  • Create a demand forecast of 1000 pieces per month.

If you run forecast scheduling on January 1, the demand forecast requirements are consumed according to the percentages that are specified earlier in this section. The following requirement quantities are transferred to the master plan:

Month

Number of pieces required

January

0

February

250

March

500

April

750

May - December

1000

Example 2

Using the forecast reduction principle Transactions - reduction key

This example shows how actual orders, which occur during the periods that are defined by the reduction key, reduce demand forecast requirements.

  • Select Transactions - reduction key in the Reduction principle field in the Master plans form.

  • The following sales orders exist on January 1:

Month

Number of pieces ordered

January

956

February

1176

March

451

April

119

Using the same demand forecast of 1000 pieces per month, the following requirement quantities are transferred to the master plan:

Month

Number of pieces required

January

44

February

0

March

549

April

881

May - December

1000

See also

Reduction keys (form)

Create and use a reduction key