다음을 통해 공유


About multisite - route validations

Important

This content is archived and is not being updated. For the latest documentation, see Microsoft Dynamics 365 product documentation. For the latest release plans, see Dynamics 365 and Microsoft Power Platform release plans.

Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012

The site dimension is mandatory and you must enter a site value on all inventory transactions. When you plan materials and resources, the program selects a route version that is based on the site of the requirement, a valid date interval, and the quantity.

These are the rules that apply for sites on route versions and route lines:

  • A route version must specify a site. A route version cannot have a blank site.

  • A route version is valid for only one site.

  • When a site is defined for a route, you cannot change the site.

  • When you enter a site, the lookup forms for resources are filtered by the site that you enter.

  • If you want to use a route at another site, you can create a new route version.

  • When you copy an existing route to a different site, the resource on the route lines is cleared, and the default resources for the route relations are also cleared because the resources are site-specific.

See also

About multisite - BOM validations