About master scheduling - demand explosion of a BOM version
Important
This content is archived and is not being updated. For the latest documentation, see Microsoft Dynamics 365 product documentation. For the latest release plans, see Dynamics 365 and Microsoft Power Platform release plans.
Applies To: Microsoft Dynamics AX 2012 R3, Microsoft Dynamics AX 2012 R2, Microsoft Dynamics AX 2012 Feature Pack, Microsoft Dynamics AX 2012
This master scheduling scenario involves the following conditions:
The site dimension is mandatory and must be entered on the demand transaction.
The site dimension is consistent. Therefore, the site for lower-level demand is the same as the site on the initial demand transaction.
A successful demand explosion of a BOM version creates a demand for each BOM line item at a specific site and, possibly, at a specific warehouse. A site-specific BOM may have a specific warehouse defined for each BOM line. Also, for each BOM line, the item's dimension settings determine whether the warehouse is required. This resulting demand for each BOM line item becomes, in turn, the starting point for additional demand explosion.
The following graphic illustrates how the master scheduling demand explosion proceeds.
See also
Master planning and multisite functionality
About master scheduling - how the BOM version is determined
About master scheduling - site and warehouse coverage, warehouse mandatory
About master scheduling - site coverage, warehouse mandatory
About master scheduling - site coverage, warehouse not mandatory
About master scheduling - site and warehouse coverage, warehouse not mandatory