Summary Element
Indicates whether the task is a summary task or the assignment is on a summary task.
<Summary>
BooleanValue
</Summary>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
Text Value
A text value of type boolean is required.
Value |
Description |
---|---|
0 |
False |
1 |
True |
Remarks
Note
You should generally assign resources to individual subtasks, not to a summary task. For more information, see Assign a resource to a task in the Project 2007 Help and How-to guide.
See Also
Task Elements and XML Structure XML Schema for the Tasks Element Assignment Elements and XML Structure XML Schema for the Assignments Element