MoveRemainingStartsBack Element
Indicates whether the beginning of remaining portions of tasks scheduled to begin after the status date, but begun early, should be moved back to the status date.
<MoveRemainingStartsBack>
BooleanValue
</MoveRemainingStartsBack>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
Text Value
A text value of type boolean is required.
Value |
Description |
---|---|
0 |
False |
1 |
True |
Remarks
The MoveRemainingStartsBack element has a rounding error. The internal work value has eight digits; the work value loses 0.001 seconds for every minute, causing a rounding error.