MoveCompletedEndsForward Element
Indicates whether the end of completed portions of tasks scheduled to have been completed before the status date, but begun late, should be moved up to the status date.
<MoveCompletedEndsForward>
BooleanValue
</MoveCompletedEndsForward>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
Text Value
A text value of type boolean is required.
Value |
Description |
---|---|
0 |
False |
1 |
True |
Remarks
The MoveCompletedEndsForward element has a rounding error. The internal work value has eight digits; the work value loses 0.001 seconds for every minute, causing a rounding error.