ACWP Element
ACWP is the actual cost of work performed up to the project status date or the current date.
For a Task, ACWP is the costs incurred for work already done on a task.
For a Resource, it is the sum of ACWP values for all of a resource's assignments.
For an Assignment, it is the costs incurred for work already performed by a resource on a task.
<ACWP>
FloatValue
</ACWP>
Parent Elements
Occurrences
Minimum: 0 Maximum: 1 |
See Also
Concepts
Task Elements and XML Structure
XML Schema for the Tasks Element
Resource Elements and XML Structure
XML Schema for the Resources Element