다음을 통해 공유


MS-OXOCAL - How to calculate the FirstDateTime for monthly and yearly recurring appointments for the Hebrew calendar.

Alternate Calendars

As you may or may not be aware, Outlook supports multiple calendars. Not only does it support multiple calendars, it also supports alternate calendar types. Some languages that enable alternate calendars are Arabic, English, Hebrew, Hindi, Chinese, Japanese, Korean, and Thai.

In Outlook 2010 you can display an alternate calendar by performing the following steps.

  1. Select File -> Options to open the options dialog.
  2. Select the Calendar option on the left.
  3. Under Calendar Options, check the box 'Enable an alternate calendar' to enable the alternate calendar drop down list boxes.
  4. Select the language and calendar type you want to use.
  5. Click OK.

When you view your calendar now you will see the date values displayed in the language you selected next to the date as it appears normally. So far, nothing has really changed other than how your calendar looks.

What happens if you want to create a monthly or yearly recurring appointment and you work with alternate calendars? You might ask yourself, which calendar should the appointment follow? How do you tell it which one to use? If you're using Outlook 2010, go ahead and try it. When you get to the Appointment Recurrence dialog everything looks normal until you select either the Monthly or Yearly recurrence option. When you select one of those options, some strange things happen that you might not have expected. You now have a choice of which calendar to use and when you switch between these options you will also see the values in a few of the drop down change to that language as well.

Did you know that not every calendar type has the same number of days in a month, or months in a year? As a test, create a yearly recurring appointment that starts on the same day for 2 different calendar types. I created one that starts on July 26th 2011 for both the Gregorian and Hebrew Lunar calendars. When I go look at July 26th 2012 I only see one of the yearly recurring appointments, the one for the Gregorian calendar. The one that I created for the Hebrew Lunar calendar actually appears on July 14th 2012.

 

How does this affect me as a developer?

Why is any of this important? If you are a developer implementing a calendaring system that synchronizes with Exchange Server you MUST be aware of this and take the calendar type into account when creating monthly or yearly recurring appointments.

Most of the properties of the RecurrrencePattern structure are fairly straight forward. However, there is one in particular that will cause you some grief if you are creating monthly or yearly recurring appointments, FirstDateTime.

The documentation provides the following description for calculating this value:

  1. Find the first day of the month of StartDate.
  2. Determine MinimumDate. For Gregorian calendars, this is midnight, January 1, 1601.For non-Gregorian calendars, this is the first day of the calendar's year that falls in the Gregorian year of 1601. For example, if the CalendarType is CAL_HEBREW, the first day of that calendar's year that falls in the Gregorian year of 1601 is 1/1/5362, which is the Gregorian date of 9/27/1601.
  3. Calculate the number of calendar months between midnight of the days calculated in step 1 and step 2.
  4. Take that value modulo Period.
  5. Add that number of months to the MinimumDate, as determined in step 2.
  6. Calculate the number of minutes between midnight that day and midnight, January 1, 1601.

 

Example

Let's walk through these steps and try to calculate the FirstDateTime for the July 26th appointment that we created for the Hebrew calendar. Along the way, we'll discover why the appointment shows up on July 14th 2012.

  1. Find the first day of the month of StartDate.
    1. This is simple enough. Our start date is 7/26/2011 so the fist day of the month would be 7/1/2011
  2. Determine MinimumDate. For Gregorian calendars, this is midnight, January 1, 1601. For non-Gregorian calendars, this is the first day of the calendar's year that falls in the Gregorian year of 1601. For example, if the CalendarType is CAL_HEBREW, the first day of that calendar's year that falls in the Gregorian year of 1601 is 1/1/5362, which is the Gregorian date of 9/27/1601.
    1. This is the first step that will usually cause confusion. Luckily, the documentation gives us the value we need for this one. Why do you think I choose to work with the Hebrew calendar to start with?
    2.  Minimum Date = 9/27/1601.
  3. Calculate the number of calendar months between midnight of the days calculated in step 1 and step 2.
    1. There are a few different ways that you could calculate this. Here's the code I used to calculate it. FirstDay is the value that we got in step 1 and MinDate is the value we got in step 2.
    2. Months = ((FirstDay.Year - MinDate.Year) * 12) + (FirstDay.Month - MinDate.Month) = 4918
  4. Take that value modulo Period.
    1. Just in case you forgot your high school math, Modulo, or Modulus, means the remainder from a division operation. In our scenario the Period value is 12.
    2. 4918 MOD 12 = 10.
  5. Add that number of months to the MinimumDate, as determined in step 2.
    1. This is the second step that will cause confusion and unfortunately the documentation doesn’t give us the answer this time. You can't just add the value from step 4 to the month value from step 2 and add a year if the new date goes past December. If you know anything about the Hebrew calendar you might know that a year can have 12 or 13 months, that a month can have 29 or 30 days, and that the lunar year has approximately 11 days less than the solar year. So, what do we do? Because the Hebrew calendar is based on the lunar cycle we will use lunar months instead of calendar months. A lunar month is 29.53 days. Take our result from step 4, which is 10, and multiply that by the number of days in a lunar month and you get 295.3 days. Drop the decimal and add that many days to the Minimum Date.
    2. 9/27/1601 + 295 days = 7/19/1602.
  6. Calculate the number of minutes between midnight that day and midnight, January 1, 1601.
    1. First we need to figure out how many days will pass between those dates. 7/19/1602 - 1/1/1601 = 564 days.
    2. Then you can multiply by 1440 minutes in a day to get the final answer. 564 * 1440 = 812160.

Using a tool like MFCMAPI, you can verify that this is correct. So, if you were a developer building a calendaring system that supported the Hebrew calendar and you need to sync with Exchange Server, that is how you would calculate the FirstDateTime field when you populate the RecurrencePattern structure.

 

Conclusion

So, can you figure out why the appointment we created on July 26th 2011 shows up next year on July 14th 2012? Go back to step 5 where we talk about the importance of the lunar month to the Hebrew calendar. The next occurrence of the appointment will be 1 year from July 26th 2011. But the lunar year has approximately 11 fewer days than the solar year. July 26 - 11 days = July 15. Well, that's not right. What's going on? Don't forget that 2012 is a leap year, so there's an extra day in February. The correct way to do it is to use the same method as in step 5, multiply 12 months by 29.53 lunar days and drop the decimal. You will see that the lunar year contains 354 days. Add 354 days to July 26th 2011, remembering that 2012 is a leap year and February has 29 days, not 28, and you will get July 14th 2012.

Comments

  • Anonymous
    January 09, 2012
    I see from your profile that you're a Microsoft employee.  You aren't involved with Windows Phone at all, are you?  'Cause Windows Phone does not handle recurring appointments on alternate calendars properly.  I really need for it to do this (particularly with the Hebrew calendar).

  • Anonymous
    January 10, 2012
    Hi Steven, you should first verify the version of Exchange Server that you are using. Per MS-ASCAL, Section 6, behavior note 2; "The CalendarType element is not supported when the MS-ASProtocolVersion header is set to 12.1 or 14.0." This means that your WP7 device must be syncing with Exchange Server 2010 SP1. Beyond that, you should try posting your question on the Windows Phone 7 developers forum. They may have more information about what is and isn't implemented in the WP7 calendar client. social.msdn.microsoft.com/.../threads