ProjectDataSet.TaskRow.TASK_FIXED_COST_ACCRUAL Property
Indicates how fixed costs are to be accrued in a task.
Namespace: [Project Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Project.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Project.asmx?wsdl
Syntax
'Declaration
Public Property TASK_FIXED_COST_ACCRUAL As Short
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Short
value = instance.TASK_FIXED_COST_ACCRUAL
instance.TASK_FIXED_COST_ACCRUAL = value
public short TASK_FIXED_COST_ACCRUAL { get; set; }
Property Value
Type: System.Int16
Remarks
1 = Start; costs are accrued as soon as the task starts, as indicated by a date entered in the ActualStart field.
2 = End; costs are not incurred until remaining work is zero.
3 = Pro-rated (default); costs accrue as work is scheduled to occur and as actual work is reported.