ProjectDataSet.TaskRow.TASK_COMPLETE_THROUGH Property
Gets the date that specifies when the task was completed.
Namespace: [Statusing Web service]
Service reference: http://ServerName:32843/[Project Service Application GUID]/PSI/Statusing.svc
Web service reference: http://ServerName/ProjectServerName/_vti_bin/PSI/Statusing.asmx?wsdl
Syntax
'Declaration
Public Property TASK_COMPLETE_THROUGH As DateTime
Get
Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As DateTime
value = instance.TASK_COMPLETE_THROUGH
instance.TASK_COMPLETE_THROUGH = value
public DateTime TASK_COMPLETE_THROUGH { get; set; }
Property Value
Type: System.DateTime
Remarks
Read-only. It is calculated as the sum of TASK_ACT_START and TASK_ACT_DUR.